The Board of Directors of Électricité du Liban (EDL) held a meeting in which it discussed "a number of files related to the institution's work, particularly the file on restarting the Zouk and Jieh plants," according to a statement. After deliberation, the Board took the following decision:
"Having reviewed the final proposal of the committee tasked with studying the restart of the Zouk and Jieh plants, as well as the relevant judicial decisions and the requirements of the ongoing judicial expertise before the State Council, and after discussion, and out of concern for the public interest, increasing electricity production, easing the burden on citizens, and safeguarding public funds, the Board of Directors has decided the following:
First: Preliminary approval of restarting the two plants. Preparations are under way to restart the units whose soundness and readiness are proven, with the operation of each unit to begin after the results of inspections and tests by the manufacturer, MAN, are documented.
Second: Implementing the measures in coordination with the relevant parties, taking into account the existing legal disputes, particularly before the State Council, and complying with the relevant judicial decisions, without prejudicing these disputes or anticipating their outcomes, and while preserving the rights of all parties. The Legal Department, in coordination with the institution's lawyer, is tasked with verifying the requirements of the decisions and measures in force, and with following up on the judicial expertise and coordinating with the expert within the scope of his mission. Before any operation, dismantling, maintenance, or replacement of parts that could affect the subject of the expertise, the technical condition shall be documented and the evidence and parts preserved.
Third: Affirming that the restart and the related measures do not constitute a discharge of the operator's liability, whether explicitly or implicitly, nor an exemption from any obligations or responsibilities. The institution's rights and claims against the operator remain fully reserved, subject to the final judicial rulings. Inspection, maintenance, or restart shall not constitute an acknowledgment of the soundness of previous work or of the validity of the disputed claims, nor an acceptance of the spare parts in dispute, nor a waiver of the institution's rights against any party concerned. In parallel, the necessary measures shall be taken to preserve the claims, guarantees, securities, and legal and contractual deadlines, without waiting for the expertise to conclude or a ruling to be issued.
Fourth: Tasking the committee with drawing on all necessary technical expertise to inspect the generating sets and equipment of the two plants, particularly the manufacturer MAN – Everllence, to determine their condition and readiness, and to draw up a clear plan for the work and tests required before operation, covering its phases and successive steps, and submit it to the Board of Directors so that it may take the necessary decisions in due course. The plan shall include identifying the units proposed for operation, the tests and work required for each unit, the sequence, scope, and cost of implementation, and the parties responsible for it.
Fifth: Separating all new inspections, maintenance, and operation from the previous disputed claims. This decision does not permit settling, acknowledging, or paying those claims, or making any payment on account of them, nor waiving any right, guarantee, or security. The contracts and expenditures required for the restart shall be submitted to the Board of Directors for approval in accordance with legal and contractual procedures."
Operating the two plants, even partially, would increase hours of electricity supply by two to three hours, and could reach 6 hours if they are fully operated.